Disappointing news from the Grove Hill Park Commission meeting this morning. With no bids solicited and no contract awarded, the half-finished projects from 2023 won’t even be able to start until the second half of this year, putting the construction of the actual park at risk.

More Delays for Grove Hill Park

More Delays for Grove Hill Park

With no bids solicited and no contract awarded, the half-finished projects from 2023 won’t even be able to start until the second half of this year, putting the construction of the actual park at risk.

The Grove Hill Park Commission met this morning, where it was announced by Chair Nancy Rogoff that bids for the remaining work to repair the Cottage Street retaining wall and planting to stabilize the adjacent hillsides would not be released until June of this year. Plans for this work were developed, approved, and budgeted for 2023. Part of the wall repair work was completed in the fall of 2023, until it stopped due to the weather.